In this episode of the Pipeliners Podcast, host Russel Treat dives into the topic of management of change (MOC) and its critical role in pipeline safety management.
Drawing on insights from recent industry discussions and conferences, the episode explores how MOC applies across different operational areas, contrasts it with other industries like plant management, and addresses the complexities of departmental versus enterprise-wide MOC processes. The episode also touches on ongoing challenges and solutions being considered at EnerSys to streamline MOC implementation.
Management of Change – a Key Component of Pipeline Safety Show Notes, Links, and Insider Terms
- Russel Treat is the CEO of EnerACT Energy Services, as well as the host of the Pipeliners Podcast and the founder of the Pipeline Podcast Network. Connect with Russel on LinkedIn.
- EnerACT Energy Services is a holding company of oil and gas technology and service companies. EnerSys Corporation is a frequent sponsor of the Pipeliners Podcast. Find out more about how EnerSys supports the pipeline control room through compliance, audit readiness, and control room management through the POEMS Control Room Management (CRM Suite) software suite.
- MOC (Management Of Change) focuses on planning the processes in a system, the type and quality of changes required, the risks associated with the plan for change, and the people that will be impacted by the change so that it is clearly communicated to stakeholders.
- Operational Controls: Procedures and systems in place to manage changes and risks within pipeline operations to maintain safety and compliance.
- API (American Petroleum Institute) represents all segments of America’s natural gas and oil industry. API has developed more than 700 standards to enhance operational and environmental safety, efficiency, and sustainability.
- API RP 1173 established the framework for operators to implement pipeline safety management systems. The PSMS standard includes 10 core elements.
- Pipeline SMS (Pipeline Safety Management Systems) or PSMS is an industry-wide focus to improve pipeline safety, driving toward zero incidents.
- OSHA (Occupational Safety and Health Administration) is an agency in the United States Department of Labor. Their mission is to “assure safe and healthy working conditions for working men and women by setting and enforcing standards and by providing training, outreach, education, and assistance.”
- Process Safety Management (PSM): A regulatory framework under OSHA that governs changes in industrial processes, particularly in environments like plants, focusing on modifications to equipment, procedures, and materials.
- Control Room Management (CRM): The set of procedures and technologies used to monitor and control pipeline operations from a central location.
- High Consequence Area (HCA): Geographic regions where a pipeline failure could have significant adverse effects, such as densely populated areas or environmentally sensitive locations.
- SCADA (Supervisory Control and Data Acquisition) is a system of software and technology that allows pipeliners to control processes locally or at remote location. SCADA breaks down into two key functions: supervisory control and data acquisition. Included is managing the field, communication, and control room technology components that send and receive valuable data, allowing users to respond to the data.
- HMI (Human Machine Interface) is the user interface that connects an operator to the controller in pipeline operations. High-performance HMI is the next level of taking available data and presenting it as information that is helpful to the controller in understanding the present and future activity in the pipeline.
- MAOP (Maximum Allowable Operating Pressure): The maximum pressure at which a pipeline is allowed to operate, as determined by regulatory standards and engineering practices.
- AGA (American Gas Association) represents companies delivering natural gas safely, reliably, and in an environmentally responsible way to help improve the quality of life for their customers every day. AGA’s mission is to provide clear value to its membership and serve as the indispensable, leading voice and facilitator on its behalf in promoting the safe, reliable, and efficient delivery of natural gas to homes and businesses across the nation.
- Enterprise MOC: Management of change processes that apply across the entire organization, affecting multiple departments or operational areas.
- Departmental MOC: Management of change processes that are limited to a specific department, focusing on changes within a localized scope.
- Pre-Startup Safety Review (PSSR): A safety protocol conducted before starting up new or modified systems to ensure that changes have been implemented correctly and safely.
- Automation: The use of technology and control systems (such as SCADA) to operate pipelines and related infrastructure with minimal human intervention, improving safety and efficiency.
- Right-of-Way (ROW): A legal right, typically a strip of land, granted for the construction and operation of a pipeline, often running through public or private property.
- Pipeline Integrity Management: The processes and procedures used to ensure that a pipeline is maintained in a safe and functional condition, preventing leaks, ruptures, or failures.
- Risk Assessment: The process of identifying, evaluating, and mitigating potential hazards associated with changes in pipeline operations or infrastructure.
- Procedural Change: Any modification to operational procedures, which may include updates to policies, guidelines, or standard operating processes for safe pipeline operations.
- Facility Changes: Modifications to physical structures or equipment involved in pipeline operations, such as compressor stations, pump stations, or valves.
- Information System Changes: Adjustments made to the software or technology systems that manage data and communications in pipeline operations.
- PLCs (Programmable Logic Controllers) are programmable devices placed in the field that take action when certain conditions are met in a pipeline program.
- Valves: Devices in pipelines used to control the flow of liquids or gases, essential for operational safety and efficiency.
- Watershed: A region or area that drains into a common water source, which can be impacted by pipeline operations if proper environmental precautions aren’t taken.
Management of Change – a Key Component of Pipeline Safety Full Episode Transcript
Russel Treat: Welcome to the “Pipeliners Podcast,” episode 359, sponsored by EnerSys Corporation, providers of POEMS, the Pipeline Operations Excellence Management System, operations and compliance software for the pipeline control operator to address safety program management, control room management, and field operations. Find out more about POEMS at enersyscorp.com.
[background music]
Announcer: The Pipeliners Podcast, where professionals, bubba geeks, and industry insiders share their knowledge and experience about technology, projects, and pipeline operations.
Now your host, Russel Treat.
Russel: Thanks for listening to the Pipeliners Podcast. I appreciate you taking the time. To show that appreciation, we give away a customized YETI tumbler to one listener every episode.
This week, our winner is Michael Kinik with Iroquois Pipeline Operating Company. Congratulations, Michael. Your YETI is on its way. To learn how you can win this prize, stick around till the end of the episode.
This week, it’s just me. I’m going to talk about management of change and its importance in pipeline safety management. To tee this up, I should talk a little bit about why this is up for me.
Back in the spring, in the AGA Operations Conference, I went to a couple of presentations and panels talking about management of change. It really spun up a whole conversation internal to our company.
We have software for control room management, for process management, for management of policy and procedures. Each of those tools has a level of management of change embedded.
One of the things I was curious about is what is the need for management of change? Is that an enterprise need? Is that a departmental need? What is the nature of that need for pipeline operators? Hopefully, this conversation can put a little problem definition on that.
Started out, in prepping for this episode, I went and did a little research. I wanted to see what other industries say about management of change, and in particular, OSHA. OSHA has requirements in its regulatory structure for process safety management, which is targeted at plants. One of the elements of process safety management is management of change.
In that context, OSHA defines change management as all those things that require modifications to equipment, procedure, raw materials, and processing conditions. In other words, anything other than a replacement in kind.
I would argue that that same definition more or less applies to pipelining. That anything we do where we’re changing the piping, the equipment, the automation, the documentation, the policies, the procedures, the fluid we’re flowing, the direction the fluid is flowing, any of those kind of thing require a management of change process.
Facility changes, control system changes, information system changes, procedural changes, those would be the four categories that typically are talked about in PSM.
Just to build a little bit more context on this, typically or historically, we have thought, if we have a need to make a change, we just determine the need, we design a solution, we construct that solution, and we place that solution into service.
In reality, MOC is more than that. MOC starts when we determine a need. The first thing we do is we determine, is an MOC required? If it’s anything other than a replacement in kind, an MOC would be required. Then we do an assessment. We do a risk assessment trying to understand the scope and the risk of the change.
We then do our design process and our construct process, but then we validate the construction. We do a pre-startup safety review. We design training and communications to notify affected parties about the change. Then we put the change into service.
Once the change is in service, we verify that we accomplished what we set about to accomplish, and we update our documentation and procedures.
Management of change is all those things around the work, where we’re educating, informing the people about the change happening in the process so that they can be effective in operating the process. In a pipeline safety management, it’s pretty much the same thing, versus a plant or OSHA PSM.
The primary difference between a plant and management of change in a plant and management of change for a pipeline — and I think this is something that we need to be mindful at all times about what we do as pipeliners, is we operate critical infrastructure, but different than those that are governed by OSHA.
Where there’s a fence around the asset and that asset has a footprint, and there’s a certain amount of training and access control just to get to the asset. Our assets operate in the public domain. They operate in right-of-ways and people’s backyards, where we’re moving the product.
Therefore, one of our key considerations is, is this change going to be in an MCA, or does it impact an HCA, a high consequence area? Does it impact a watershed? The risk management frame is different than it would be in a PSM.
Management of change is an operational control. It’s a way to keep control of the operation as changes are being made to improve, or add to, or take away from a process.
In the PSMS standard, API 1173, management of change is in the operational controls area. The requirements are that operators shall maintain procedures for management of change, that management of change procedure should address all changes, both permanent and temporary, of a technical, physical, procedural, and organizational manner. Again, it’s throwing a very wide net.
The MOC procedure should consider and evaluate the reason and implication of the change, the acquisition of required work permits, the requisite documentation and communication of the change to relevant parts of the organizations.
Going back and talking about the conversations that were occurring in the spring at AGA Operations, one of the big conversations is around enterprise MOC versus departmental MOC. Let me try to elaborate on that.
If I am the SCADA manager and I’m responsible for delivering screens to the control room, and I make a change on the screen that only the control room’s going to see, then I don’t necessarily need to communicate that change to all the other departments.
One of the conversations that occurred was an organization had talked about they started by sending all changes to a central point. All changes went to the change coordinator in each department.
They said whether or not they needed to look at that change, which created a large administrative burden and a whole lot of things that were being looked at and said, “That doesn’t apply to me,” which is not an effective process. It’s not an efficient process.
Likewise, there’s a conversation about, if I do a change that’s within a department — again, I’ll use a change on a SCADA screen — how do I know that doesn’t affect others? For example, if I update an MAOP label on a pipeline in a screen, should that be verified in the engineering department?
It seems trivial, but those are the kinds of things that can lead to problems. They can lead to things being misidentified. They can lead to incorrect decision-making and increased risk of operation. What is the appropriate level of review and analysis to determine the scope and risk of a change? It’s really quite a complicated problem.
Likewise, some changes required different kinds of solutions. Oftentimes, when I’m working a change, I need to work that change in the tool that’s appropriate for the change I’m making. For example, if I’m making a change in the SCADA system, I’m going to be using the SCADA platform to make that change.
If I’m making a change in engineering, then I’m going to be modifying drawings. If I’m making changes in a procedure, I’m going to be modifying documents. The closer I get to the change actually being made, the more the change I’m making is tied to the tools I’m using.
It makes sense for there to be departmental MOCs and for there to likewise be enterprise MOCs. If I’m adding a new loop in a gas distribution system, then that’s going to have multiple departments, multiple organizations needing to look at that.
There’ll be things about what equipment’s going to be on that pipeline? Who’s going to be servicing that line? Are we going to need new procedures for operating that line? That becomes a lot more involved and complex.
The real challenge, I think, for anybody who’s looking at MOC and trying to understand how to make it actually add value is this whole administrative analysis, understanding the scope and risk of the change.
That process, if you will, for determining the scope and risk of a change is across departments. This is a list. It might not be comprehensive or inclusive of everything, but it gives you an idea. Operations and maintenance would be a department.
Asset management, integrity management, organizational structure, supplier and contractor agreements and the services they’re providing, tools and equipment. That could include things like telecommunication equipment, programmable logic controllers, valves, just a whole long list of things.
Every change that’s being made in the organization, if I’m going to fully follow PSMS, needs to follow MOC. I need to have a mechanism for determining the scope.
The question I would ask is, is it more effective to have every MOC go through a central place, and for that central place to send those out to everybody, everybody looks and says, “No, it doesn’t affect me,” or is it more appropriate that MOCs have sponsors?
In other words, the organization that’s queuing the MOC up is the sponsor, and then the sponsor has responsibility to determine impact. I argue that because I think that that is a more efficient way to work the MOC.
Likewise, if a MOC is originated within a department and then that department makes a determination that it only affects the department, and they should be able to manage and implement the MOC without involving others, then that’s perfectly acceptable.
I need a mechanism at some level to see every MOC in the company and to do some kind of quality analysis to determine if the MOC was properly scoped, if risk was properly assessed, and if the change was properly implemented.
I’m teeing all this up just to say this is something that we’re thinking about at EnerSys. It’s a non-trivial problem, to say the least. It’s a spider web. My thinking is that you need a system that will allow each organization to sponsor and initiate its own MOCs. Then there’s got to be a mechanism for recording and keeping all that in a single repository.
We have some ideas about that. The complexity is just getting clear about the model, about how is it originated, and then how is it scoped and evaluated? If it’s originated at a lower level going up, how does that work?
Anyways, I’d be very interested, if anybody has thoughts on this subject, if you’d drop me a note, either on the Contact Us page at pipelinepodcastnetwork.com, or you can reach out to me on LinkedIn and drop me your thoughts about this.
I’d love to get some people that are working on this problem onto the podcast, talk about it. I know there’s a lot of operators that are working through this and struggling to try and find the right answer. We’re certainly working on some things ourselves to try and do that as well.
Anyways, that concludes this week’s episode of the Pipeliners Podcast. I hope you enjoyed the conversation. I hope I was able to queue up a little thinking. Just a reminder, you should register to win our customized Pipeliners Podcast YETI tumbler. Simply visit pipelinepodcastnetwork.com/win and enter yourself in the drawing.
If you’d like to support us, best way to do that is to leave us a review. You can do that wherever you happen to listen.
[background music]
Russel: Then lastly, if you have ideas, questions, or topics you’d be interested in, please let me know, either on the Contact Us page at pipelinepodcastnetwork.com, or reach out to me on LinkedIn. Thanks for listening. I’ll talk to you next week.
[music]