In this episode of the Pipeliners Podcast, Keith Coyle from Babst Calland provides a regulatory update focused on recent litigation involving PHMSA rulemakings. He discusses two major cases—GPA Midstream Association vs. the Department of Transportation and INGAA vs. PHMSA—and explains their significance for the pipeline industry. Keith delves into the legal challenges regarding PHMSA’s rulemaking process and the impact these rulings may have on future regulations.
Regulatory Update and Recent GPA and INGAA Cases Show Notes, Links, and Insider Terms
- Keith Coyle is a shareholder and attorney with the law firm of Babst Calland. Mr. Coyle is a member of the firm’s Washington, D.C. office and a Shareholder in the Pipeline and HazMat Safety practice. Connect with Keith Coyle on LinkedIn.
- Babst Calland’s Energy and Natural Resources attorneys work collaboratively across legal disciplines to serve the needs of energy companies across the United States. Based in Washington, D.C., the Firm’s Pipeline and Hazardous Materials Safety practice represents clients on all types of pipeline safety and hazardous materials transportation matters.
- PHMSA (Pipeline and Hazardous Materials Safety Administration) is responsible for providing pipeline safety oversight through regulatory rule-making, NTSB recommendations, and other important functions to protect people and the environment through the safe transportation of energy and other hazardous materials.
- Notice of Proposed Rulemaking (NPRM) is a stage in the rulemaking process that happens before an agency adopts a final regulation. It is like the first draft of a regulation and gives the public an idea of what is to come.
- NTSB (National Transportation Safety Board) is a U.S. government agency responsible for the safety of the nation’s major transportation systems: Aviation, Highway, Marine, Railroad, and Pipeline. The entity investigates incidents and accidents involving transportation and also makes recommendations for safety improvements.
- Natural Gas Pipeline Safety Act of 1968 (Pipeline Safety Act) was authorized by the Secretary of Transportation to prescribe safety standards for the transportation of natural and other gas by pipeline, and for other purposes.
- GPA or GPA Midstream Association is a voluntary industry organization composed of member companies that operate in the midstream sector of our industry. GPA Midstream sets standards for natural gas liquids; develops simple and reproducible test methods to define the industry’s raw materials and products; manages a worldwide cooperative research program; provides a voice for our industry on Capitol Hill; and is the go-to resource for technical reports and publications.
- Leak Detection and Repair (LDAR) is the process by which oil and gas, chemical, and/or petrochemical equipment is monitored for the location and volume of unintended leaks
- Gas Mega Rule – The rule, initiated over 10 years ago, expands the definition of a “regulated” gas gathering pipeline that is more than 50 years old. It will—for the first time—apply federal pipeline safety regulations to tens of thousands of miles of unregulated gas gathering pipelines.
- API (American Petroleum Institute) represents all segments of America’s natural gas and oil industry. API has developed more than 700 standards to enhance operational and environmental safety, efficiency, and sustainability.
- The San Bruno or PG&E Incident in September 2010 refers to a ruptured pipeline operated by the Pacific Gas & Electric Company. The rupture created a crater near San Bruno, California, caused an explosion after natural gas was released and ignited, and resulted in fires causing loss to life and property.
- Valve and Rupture Rule is a newly updated PHMSA regulation. This rule establishes requirements for rupture-mitigation valves, such as spacing, maintenance and inspection, and risk analysis. The final rule also requires operators of gas and hazardous liquid pipelines to contact 9-1-1 emergency call centers immediately upon notification of a potential rupture and conduct post-rupture investigations and reviews.
- Gathering Lines are pipelines that transport natural gas from production facilities to a transmission line or distribution main lines.
- Type A: Pipelines that operate at relatively higher stress levels and are located in locations that have more than 10 buildings intended for human occupancy or locations where buildings with four or more stories above ground are prevalent.
- Type B: lines operating at lower pressures/stress levels than Type A lines in class 2, 3, or 4 areas.
- Type C: gas gathering lines in Class 1 locations that have an outer diameter of 8.625 inches or greater and operate at an MAOP producing a hoop stress of 20% or more of SMYS, or if the pipeline is non-metallic or the stress level is unknown, operates above 125 pounds per square inch gauge.
- Leak Detection and Repair (LDAR) is the process by which oil and gas, chemical, and/or petrochemical equipment is monitored for the location and volume of unintended leaks
- LPAC (Liquid Pipeline Advisory Committee) and GPAC (Gas Pipeline Advisory Committee) are statutorily mandated advisory committees that advise PHMSA on proposed gas pipeline and hazardous liquid pipeline safety standards, respectively, and their associated risk assessments. The committees consist of 15 members with membership evenly divided among Federal and State governments, the regulated industry, and the general public. The committees advise PHMSA on the technical feasibility, reasonableness, cost-effectiveness, and practicability of each proposed pipeline safety standard.
Regulatory Update and Recent GPA and INGAA Cases Full Episode Transcript
Russel Treat: Welcome to the “Pipeliners Podcast,” episode 354, sponsored by Solarcraft, providing high-quality engineered solutions for powering, sheltering, and operating critical field automation infrastructure. Find out more about Solarcraft at solarcraft.net.
[background music]
Announcer: The Pipeliners Podcast, where professionals, bubba geeks, and industry insiders share their knowledge and experience about technology, projects, and pipeline operations. Now your host, Russel Treat.
Russel: Thanks for listening to the Pipeliners Podcast. I appreciate you taking the time. To show that appreciation, we give away a customized YETI tumbler to one listener every episode. This week, our winner is Joaquin Repollet with Eversource. Congratulations, Joaquin. Your YETI is on its way. To learn how you can win this prize, stick around till the end of the episode.
This week, Keith Coyle, with Babst Calland, returns to provide us a regulatory update and discuss the recent GPA and INGAA cases. Keith, welcome back to the Pipeliners Podcast.
Keith Coyle: Hey, Russel. It’s always good to be on here. It’s been a little while. I’m not quite sure what we talked about last time. It might have been talking about the leak detection and repair rule a couple months ago.
Russel: Yeah, that was back in March. That’s nearly six months ago now, which I don’t think, since we started having you on as our regulatory guru, that we’ve gone that long without talking. What’s going on in the PHMSA regulatory world?
Keith: I know you reached out and you wanted to have a conversation today about PHMSA-related litigation, particularly involving rulemakings. There are two cases that I was hoping to discuss today.
One is a case from last year, GPA Midstream Association v. the Department of Transportation, and another one is a case that came out last week, that’s the Interstate Natural Gas Association of America vs. the Pipeline and Hazardous Material Safety Administration.
Both of those cases involved challenges to recent PHMSA rulemakings, and I think they can provide some valuable insights for the listeners both on how PHMSA’s rulemaking process works, how the process of challenging a PHMSA regulation unfolds over time, and how the end results of litigation can impact rulemakings on a go-forward basis.
Russel: Let’s talk a little bit about the GPA case. We’ve talked about that before. Why don’t you give us a little background to remind the listeners what that’s all about?
I’ll just say that the GPA primarily represents gatherers. They’re the Gas Processors Association. That’s typically gas gathering, gas processing. Why don’t you tell us a little bit about that case and their specific complaint?
Keith: The GPA case was actually GPA Midstream Association and the American Petroleum Institute. They brought a challenge in federal court to a final rule that PHMSA issued involving the use of rupture mitigation valves.
Before I dive into the weeds on that challenge, I think it might be a little bit helpful for the listeners if I start with a little bit of a background on litigation and judicial review in PHMSAland generally.
Under the Pipeline Safety Act, there is a judicial review provision that authorizes challenges to certain kinds of final agency actions that PHMSA takes, two big kinds of final agency actions, one, final rules or regulations, and then two, final orders in other proceedings.
There is a deadline that’s prescribed in the statute for when you need to take one of those kinds of challenges. It’s 89 days from the date when the action is taken.
The place where you take those cases when you go to federal court is actually the federal appellate courts. You don’t take your challenges to PHMSA regulations or PHMSA final orders to district court, which is the trial-level court in the federal courts.
You take them up to the federal appellate courts, which is the next level in the federal judicial system. It’s one step down from the Supreme Court. That’s a little bit unique in that PHMSA has this specific judicial review provision. There’s an 89-day deadline.
It tells you, if you are going to challenge one of these PHMSA actions, you need to bring that challenge in a federal appellate court, either the DC Circuit, which is a federal appellate court that sits in DC and hears a lot of agency cases, or another federal appellate court where venue is proper based on the party bringing the challenge.
That’s the foundational basics on how you bring a challenge to PHMSA action, what the deadlines are, and then where those challenges go.
Russel: I have to ask maybe a college-level political science question. Why does that start in the appellate court rather than in the trial court?
Keith: That’s a good question. In some agency proceedings, you can take your challenge to the district court. Not all agency judicial review provisions are created equal. PHMSA has a specific judicial review provision that funnels challenges to the federal appellate courts.
On the rulemaking side, the primary idea is you already have a pretty extensive record that’s built as part of that administrative proceeding for the court review. Usually, when you’re taking things to a trial court, you’re taking it to a trial court to build a record in the first instance, to have witnesses show up, to have evidence be introduced, that kind of thing.
When you’re dealing with rulemaking challenges, there are quite a few agency statutes that direct those types of challenges to the federal appellate courts. Then PHMSA has the same for its enforcement proceedings, too, where the record is built before the agency. Then you take that challenge to the federal appellate court as well.
Russel: That actually makes sense. What you’re saying is the nature of the process is that it is deliberative and adjudicated by its nature. Consequently, if somebody has a concern or a grievance, then it really is an appeal to a process that’s already been worked through a deliberative process.
Keith: Yeah. The basic concept is you’re building the record in an agency proceeding, either through a rulemaking or through some kind of enforcement case. There are agency proceedings…One I can think of is Social Security Administration cases. I think those go to district court. I think you can get a trial de novo or a new trial, basically, in district court.
At least for PHMSA and quite a few other federal agencies that I’m familiar with, they challenge judicial review of agency proceedings to the federal appellate courts.
One of those federal appellate courts that I mentioned, the DC Circuit, they have a lot of agency challenges that are directed to that court because agency administrative law expertise is handled in that court. They hear a lot of agency proceedings. There are quite a few administrative proceedings that get channeled up to the DC Circuit.
You can bring challenges in other federal appellate courts under the Pipeline Safety Act if you have proper venue. We see them a lot of different places, but the DC Circuit is generally the one that gets the most agency cases in the federal appellate courts.
Russel: Interesting. Very good. Tell us a little bit about where we are with the GPA case.
Keith: In GPA, there was a PHMSA regulation that was issued back in, I think it was, 2022 — I’m showing my age — might have even been [laughs] earlier than that. It was a final rule that was issued, dealing with a requirement to have rupture mitigation valves installed on pipelines.
That rulemaking was actually the result of a statutory mandate that Congress had included in the 2011 reauthorization of the Pipeline Safety Act. There was a statutory mandate that was put in that directed PHMSA to issue regulations requiring the use of rupture mitigation valves on certain transmission lines.
That mandate was in direct response to the San Bruno gas transmission line failure that happened a few years earlier, where one of the concerns that was highlighted from that incident was an inability to close valves fast enough that would have isolated that segment and caused less damage.
Based on the National Transportation Safety Board recommendations from the investigation of that incident, Congress included this mandate in the 2011 act, telling PHMSA to go do a regulation on it.
Fast-forward, PHMSA issues a proposed rule. In the proposed rule, PHMSA did propose to apply these rupture mitigation valve requirements to transmission lines, but based on the language in 192…Part 192 is PHMSA’s regulations for gas pipelines. Part 195 is PHMSA’s regulations for liquid pipelines.
Because of the cross-referencing that occurs in the regulations between gathering lines and transmission lines, when PHMSA proposed to require the use of these valves on transmission lines, it was also proposing to require them on gathering lines.
GPA and API, when they looked at the proposed rule and pulled together their comment letter, they went back to PHMSA and said, “Hey. Wait a minute. Because of the cross-referencing with the rules here, these regulations would actually require rupture mitigation valves on some gathering lines as well.
” We don’t think that that’s what the agency intended because there’s nothing else in the rulemaking, at this point, to indicate that. There was no analysis of requiring rupture mitigation valves on gathering lines in the preliminary cost-benefit analysis. There was no discussion of it in the proposed rule.”
API/GPA pointed that out in their comments. Then when we got to the the federal advisory committee process, the GPAC, which we talked about a few episodes ago, GPA and API raised those concerns again about the absence of data and information related to gathering.
The GPAC and LPAC provided recommendations back to PHMSA. “You should take a second look and consider whether you should do this in a separate rulemaking.” PHMSA went ahead in the final rule and still required the installation of rupture mitigation valves on certain gathering lines.
GPA and API decided to seek judicial review or challenge that aspect of the final rule in the DC Circuit, which is that federal appellate court that we talked about a little bit ago.
Russel: Where are we with that case? The court issued a decision. Isn’t that correct?
Keith: Yeah. GPA and API, their primary argument before the court was that PHMSA failed to comply with the cost-benefit requirements in the Pipeline Safety Act, in developing the proposed rule and the final rule.
The court issued a decision in May of 2023 agreeing with GPA and API on that front. The court emphasized, one, there was no discussion of gathering lines in the preliminary cost-benefit analysis or in the proposed rule.
They noted that the advisory committees had flagged that as a concern and asked PHMSA to consider to do things separately and that the analysis that PHMSA provided in the final rule, of why it was cost-beneficial to include this requirement for gathering, didn’t satisfy the reasoned determination requirement in the Pipeline Safety Act.
What the court did was they vacated or invalidated that final rule as it applied to gathering lines.
You’re probably familiar. When PHMSA issues a final rule and they’re going to change a whole bunch of regulations in a final rule, when you bring a challenge into federal court, you’re the master of the challenge that you want to bring. You get to pick the arguments that you want to make and the regulations that you want to challenge.
In this case, GPA and API argued, “We think that this final rule should not be applied to gathering lines.” The court agreed with that. They basically said, to the extent that there was anything in this final rule that said gathering lines, that’s invalidated or vacated.
Then the agency, PHMSA, came back later and revised the previous final rule to essentially delete any of the provisions that refer to gathering lines. That happened last year, I think in August of 2023. The court decision came out in May. I think by August of 2023, PHMSA had issued a revised final rule deleting the gathering line requirement.
Russel: Do you anticipate, Keith, that PHMSA will reengage that requirement in a future rulemaking, or is that just off the table until there’s a new congressional mandate?
Keith: I don’t think it’s off the table. I think PHMSA has, I believe relatively recently, asked for some additional data and information regarding the use of valves on gathering. One of the arguments that GPA and API made in the case was that, because of the limited nature of that rulemaking mandate, PHMSA couldn’t require rupture mitigation vows on gathering lines.
The court disagreed with GPA and API on that. They said that PHMSA has the legal authority to do it. They just didn’t follow the proper procedures in requiring rupture mitigation valves in that final rule.
I do expect that PHMSA will continue to gather appropriate data and, at some point in the future, will make a decision about whether and to what extent rupture mitigation valves should be required on gathering lines.
We’ve talked about this before. The rules for gathering lines have really changed quite a bit, from PHMSA, in recent years, particularly on the gas side. It’s been a moving target. There have been a lot of changes.
Sorting out the impact of those rule changes, that’s still going on now. I don’t know when PHMSA will come back on this issue of rupture mitigation valves for gathering or making changes to other regulations for gathering.
I do know, on the LDAR rule we talked about last time, they are proposing to require new leak detection and repair requirements for gathering. I do expect more regulations to come on the gathering front. I’m just not sure when.
Russel: I would concur with it. What I’m wondering about is, are they going to take all that back through the GPAC? I would assume the answer to that’s probably yes.
Keith: Yeah. Procedurally, they would need to do that, unless there’s some exception to notice and comment where they could publish a final rule without going though the notice and comment process, they would need to re-propose, to do a new proposed rule, to require rupture mitigation valves.
Then you would have a period of public comment. Then all of that information would be presented to the advisory committee for consideration, then sent back to PHMSA for publication of a final rule.
Russel: We’ve been talking about the GPA rule. That’s all stuff that was completed in the court in mid-’23. Now we have a new ruling coming from the court about an INGAA complaint. Why don’t you lay out for us what that’s all about?
Keith: The new case that just came out last week, that was also a decision from the DC Circuit, so that same federal appellate court I talked about before. INGAA actually brought a challenge to a different regulation.
Way back in 2011, PHMSA actually started a rulemaking process that became known as the Mega Rule. That rule was so big that PHMSA eventually broke it up into three parts. There was Part 1, or RIN 1, that dealt with some issues for gas transmission lines.
Then there was Part 2, or RIN 2, which is the rule we’re going to talk about now, which was other related amendments for transmission lines. Then there was Part 3, or RIN 3, which dealt with gas gathering lines, which we’ve already talked about on a previous episode.
When PHMSA issued this Part, or RIN 2, final rule, in…I believe that was also in 2022, they issued a final rule in that case. INGAA took a look at the final rule and decided to file a petition for reconsideration on five of the specific standards that were included in that RIN 2 rule. That was a really lengthy rule. It changed all kinds of requirements and all kinds of different regulations.
PHMSA went back to the agency after that rule was issued and filed what is known as a petition for reconsideration. That is something that you can do in the rulemaking process. PHMSA has it, other agencies have it.
When you issue a final rule, you can go back to the regulator within a certain amount of time, in PHMSAland, it’s 30 days, and you can petition or ask the regulator to change certain provisions in the final rule that they just issued.
PHMSA filed one of these petitions with PHMSA for reconsideration, and they asked them to reconsider five specific standards. Two of those standards related to repair criteria for high-frequency ERW pipe and repair criteria for crack or crack-like anomalies.
They also asked PHMSA to reconsider a requirement for monitoring of corrosive constituents. There was a safety factor that PHMSA had in the rule for determining the reassessment intervals for dents.
Then the last one dealt with excavation requirements for pipeline segments that are subject to stress corrosion cracking.
To keep things at a high level, out of this really big rule, INGAA came back to PHMSA, petitioned for reconsideration on these five standards. They asked for some other ones, but we’ll just focus on the five. PHMSA eventually denied INGAA’s petition for reconsideration on those five standards.
INGAA sought judicial review in the DC Circuit. They filed a petition. They argued a couple of different things, but again, as in the GPA case, they also argued that PHMSA failed to comply with the cost benefit requirement as to those five standards.
The court issued its decision last Friday agreeing with INGAA on four of the five standards.
On the fifth standard, because the parties eventually agreed as the litigation spun out that they was an agreement on how PHMSA was trading pipeline segments for purposes of the stress corrosion cracking requirements, that issue fell away. On the four other standards, the court agreed with INGAA and vacated those provisions for PHMSA’s failure to comply with cost-benefit requirements.
Russel: What’s interesting to me about that is that’s thematic in both of these two instances. I wouldn’t say that’s thematic across the life of PHMSA. I don’t mean to say that at all.
In these two specific cases, that is a theme, “Oh, well, we’re doing something. We’re going to throw a little bigger net, and then we don’t do the cost-benefit analysis on the bigger net.”
Keith: Yeah. The theme on both cases is there’s a requirement in the Pipeline Safety Act that PHMSA needs to do a cost-benefit analysis, both at the proposed rule stage and at the final rule stage. In both cases, the court found deficiencies in either or both of those things, and I think this is an area where PHMSA is going to be paying greater attention in the rulemaking process.
You and I already know that, because we sat through the GPAC on the LDAR rule back in December and March. There were pretty extensive discussions about cost-benefit issues because it had already become a bigger concern because of the GPA case. The INGAA case is reinforcing the importance of the cost-benefit requirement in the Pipeline Safety Act as part of the rulemaking process.
Russel: [laughs]
Russel: That’s exactly where I was going, Keith, is I think that, with the LDAR rule, we may be headed to the same kind of thing, because there’s some pretty strong objections, particularly from GPA about the LDAR rule. Along the same lines is their complaints about the rupture valve rule.
Keith: Not just GPA. There were a lot of different sectors of the industry that have concern with the cost-benefit analysis. The other thing that I will emphasize, too, is it’s not just an industry provision, the cost-benefit requirement.
Having followed litigation with other federal agencies, it works both ways. PHMSA needs to do cost-benefit analysis. Safety advocates, environmental organizations, other members of the public, they can avail themselves the same way that industry can of concerns with cost-benefit analysis during the rulemaking process.
While both of the cases that have come up in recent years have involved industry concerns with that, I don’t think that this is going to be just an industry issue on a go-forward basis. You’ll have the concern on both sides because anytime PHMSA is going to change a rule or create a new rule, both sides are going to have their views on cost-benefit and where the rules should go for those purposes.
Russel: You make a good point. Certainly, this is just the nature of the world we live in. I’ll just make a few comments. I’d just like to hear your response. One is that this information is much more available.
When I say information, I mean information about the rulemaking is much more available than it historically has been, because of the Internet and because of individual groups that are interested in very specific issues. They have the ability to get the information and get it quite deeply and quite quickly, as opposed to where we were even 10 years ago.
Keith: The other thing is, when I started with PHMSA, people said, “You do who for what?” Now, with all of the concerns with energy transition and climate change, there’s a lot more public interest in pipelines than when I started doing this work.
We’ve seen that increased public interest in all of the recent rulemaking proceedings, that additional level of scrutiny. Anytime you have more interest and scrutiny and people involved, there’s going to be just more people involved in the rulemaking process, which creates more potential for concerns.
Russel: I think PHMSA as an agency is under much more pressure from the public than what it has historically been.
Keith: Yeah. None of these things should be taken as…I have a lot of good friends at PHMSA, or at least I tell myself I do.
[laughter]
Russel: There’s a lot of good people at PHMSA doing very good work, for sure.
Keith: That’s my point. Look, these rules are not easy. That’s why it takes so long. That’s why they take so long getting…
Russel: No, and they’re navigating through numerous organizations and their opinions, oftentimes, that are at extreme opposite perspectives. It’s very much not easy to do, but it’s important work that they’re doing.
The thing is, our process, in the US and with our government, works better when it’s slow and deliberative. Yet the public often is not patient for slow and deliberative. There’s always the push-pull of these conflicting interests.
Keith: They’ve got a big job. There’s not a lot of people out there that are doing the work for them. They’re doing the best they can. They’re going to get these decisions, take a look at the results, try to find ways to make the rulemaking process better, try to make sure they’re considering all the input, looking at all the issues.
I know they’re going to have a higher expectation from industry and other advocates as well. They’re going to take these cases and come back to us collectively and say, “If the courts are telling us these analyses need to be done better, it’s incumbent on you folks to help us with that, to come forward with more data and information, to be better advocates, be better participants.”
For a long time, PHMSA was not caught up in a lot of the crosshairs on some of this stuff. They weren’t involved in as much litigation. It was a smaller, under-the-radar agency, particularly when I started to do this work. That’s not the reality anymore. There’s more pressure. There’s more scrutiny. You’re going to have growing pains as part of that. That’s just natural.
Russel: It’s just all part of it. I do have one other question I want to ask you. [laughs] Keith, I’ve always brought you on, and I’ve always asked you a question that was a little out of left field.
Keith: This is that question, where you’re…
Russel: This is that question.
Keith: going to ask me something, and I’m going to try to think about it before I really want to answer, then I’m going to give you my answer?
Russel: Yes. Exactly. There was recently a Supreme Court decision related to a Chevron case that’s been out there for a long time and had to do with, I believe, EPA governance actions around Chevron operations.
I’m curious. My understanding of that case is the Supreme Court said the agencies can’t make law. That’s probably a gross oversimplification. I’m wondering what your perspective is on all this, given that you work in this domain?
Keith: Your synopsis…
Russel: Help me get educated about the reality versus what I’ve read in the press.
Keith: That was pretty close. There was a Supreme Court case. It was called, “Loper Bright.” It overturned an earlier Supreme Court case that was issued in the 1980s that was called, “Chevron.” Chevron was a doctrine that afforded agencies deference in interpreting their statutes where those statutes were silent or ambiguous.
Basically, it was a doctrine that gave agencies more power to tell the courts what their statutes mean. What the court said in Loper Bright, “Look, we did this Chevron experiment for a couple of decades. It turns out that that’s not what we think is right.
” We think that the job of interpreting statutes falls with the federal courts, that federal courts have an independent obligation to review statutes and decide what they mean. That doesn’t mean that we totally ignore what agencies have to say about their statutes. We listen to that stuff. It can be persuasive, particularly if agencies have been consistent over time.”
That was what the Chevron case was basically about, where if you have a statute that an agency is administering, who gets to decide what the statute means, who gets deference. Under Chevron, agencies got more deference. Now, under Loper Bright, the agencies aren’t going to get that deference. The courts are going to take on a much more important role.
It’s an interesting and impactful decision. There weren’t a lot of PHMSA cases — in fact, I can’t think of any — that went up into the courts anyways that involved Chevron deference, but Chevron, I think, is probably the most cited Supreme Court case or something close to it. It was heavily relied on in administrative law.
Now we live in what everyone is saying is a post-Chevron world. We’ll see how all that shakes out. That was a long-winded answer to your left-field question, but I am impressed that you are moonlighting by reading of or about Supreme Court decisions in administrative law.
Russel: [laughs]
Russel: Maybe I secretly desire to be a lawyer. No. No. No. That’s not true. [laughs]
[crosstalk]
Russel: It’s very interesting. One of the things that’s going on…People tend to overreact to Supreme Court decisions, just in general, in the body politic. They tend to make too much of them. What this really does is it just moves the pendulum more in the other direction.
Keith: That’s right. It takes a thumb off the scale.
Russel: It doesn’t take all the power away from the agencies. It just says, “No, agencies, you guys need to tread lightly about the boundary between doing what the law requires and making law.”
Keith: It does adjust the incentives on how agencies will act. When agencies knew that they had Chevron in their pocket, there were incentives to say that statutes weren’t clear or that statutes were silent, because agencies, having worked for an agency, you always wanted deference. A lot of times, in court, when you’re getting deference, you’re winning, so that’s what you want.
Now, because that incentive is no longer there, I do think it will help to police the boundary a little bit more, within agencies, on how aggressive they’re going to be in interpreting their statutes, how far they want to go on this stuff.
I’ll also say, at the end of the day, they have very smart lawyers at the agencies. They have very smart lawyers in Department of Justice. They are still going to win their fair share cases. The administrative state is not going to grind to a halt.
Russel: [laughs]
Russel: I thought it was the right decision, having been on both sides of the Chevron aisle over the years, probably more so, selfishly, now [laughs] because it helps my practice a little bit to not have to go up against that deference. An interesting case.
Russel: What’s happening, Keith, to be honest, is, with the work I’ve been doing the last 10 years in pipeline safety and with yourself and some of the other attorneys I know in this space that we occasionally work with, I’m gaining interest in this stuff.
I’m just picking up attorney stuff by osmosis. Very dangerous when an engineer starts thinking that they’re an attorney. Likewise, the other way around.
Keith: I was going to say the same.
Russel: Just to be clear, I am not an attorney. Nor do I aspire to represent myself as such. I do have curiosity.
Keith: I’m an attorney who tries to talk like I’m an engineer. You should have seen me when I first started at PHMSA. I was totally underwater with all the engineering stuff. I was a political science guy, no engineering background. Basic math was a challenge. I’m in these meetings, people talking about MAOP and SMYS and stress, and I’m like, “I don’t know what these people are saying.”
Russel: [laughs]
Russel: That is a humbling and continues to be a humbling process, to try to learn the engineering side.
Russel: Back at you, buddy. I didn’t used to know what adjudication was. Now I know.
Keith: [laughs]
Keith: I can actually use that word in a sentence, and probably appropriately. [laughs]
Keith: Just don’t use any Latin. Using the Latin is a giveaway that you’re trying too hard, so stick with the plain talk.
Russel: [laughs]
Russel: Oh my gosh. Now I’m going to nerd out. Anyways. Look, great to have you on. It’s been too long. Thanks for catching us up on what’s going on. We’ll be checking back in. I’ll bet there’ll be some interesting developments towards the end of the year. We’ll see.
Keith: I look forward to coming back and getting the next question from left field. It’s always fun.
Russel: You’re raising the bar on me. I’m having to stretch harder and harder to come up with the left-field questions.
Keith: I don’t want you doing any research before the show or anything like that.
Russel: [laughs]
Russel: It’s got to be a cold question. Otherwise, it’s not fair.
Russel: Exactly. That’s reasonable. Yes. [laughs] All right, Keith. Great to have you.
Keith: Thanks, Russel. We’ll talk again soon.
Russel: I hope you enjoyed this week’s episode of the Pipeliners Podcast and our conversation with Keith. Just a reminder before you go. You should register to win our customized Pipeliners Podcast YETI tumbler. Simply visit pipelinerspodcast.com/win and enter yourself in the drawing.
If you’d like to support the podcast, please leave us a review. You can do that on Google Play, Spotify, wherever you happen to listen.
[background music]
Russel: If you have ideas or topics you’d be interested in learning about, please let me know on the Contact Us page at pipelinepodcastnetwork.com, or reach out to me on LinkedIn. Thanks for listening. I’ll talk to you next week.
[music]